Hi,
I'm implement MPS in our company and I have some doubts regarding Capacity Planning Reports because I hasn't been able to offset my capacity before release my MPS plan.
I have a operation that takes weeks to be accomplished and my work center has a certain capacity. However, when I use the capacity planning report (Load or Availability) it doesn't split my operation total time through the days available. It just sum the total operation time (setup and run time) and load its due date (according with the Execution day). For example, I have a work center that works 7hr daily (mon-fri),therefore my daily capacity is 420 min. I have an operation that takes 5 days to accomplish and his run time is 2100 min (5 days x 7 hr x 60 min) and it due date is day 5 (Execution day = 5). It should shows me that my capacity from day 1 to 5 is fully load with availability from day 6. However, Xtuple shows that I have capacity available from day 1 to 4 and my day 5 is overloaded in -1680min (capacity: 420min, load: 2100min).
How can I see that this particular operation is loading my days according my finite capacity?
Has anything that I am missing or this is the way that operation works on Xtuple?
Thanks,